The solution
PFISTERER and Hellenic Cables are continuing their established partnership and working on the impressive land-sea cable connection that will safely link the Peloponnese to the 400 kV grid in central Greece. To this end, PFISTERER will supply MSA high-voltage joints and outdoor terminations, which ensure a safe transition between the submarine cables with a cross-section of 1,200 mm² and the land cables with 2,500 mm². PFISTERER also takes care of the professional installation of the sleeves and terminations, USING specialized fitters. With special system tests up to 420 kV, PFISTERER ensures that the entire system meets the strict requirements of the Greek grid operator.